TMT supplier on barter for Vasai sites: fe500 / Fe500D / Fe550D TMT from primary mills (JSW, Tata Tiscon, SAIL, Jindal Panther, Vizag) delivered to site and settled in flats, shops or units — not cash.
Vasai is Vasai Road station, Evershine City, Vasai East's industrial belt, the fort and the Catholic villages on the west, with mid-income projects spreading along the Vasai–Nalasopara link road.
Mid-income projects of 10 to 22 floors with 1 and 2 BHKs in Vasai East and Evershine, low-rise and bungalow plots on the west.
TMT comes in on 6- and 10-wheelers at night, 12 m lengths where the road allows and cut-and-bend from our yard where it does not. Deliveries are timed to the bar-bending schedule so nothing sits on the road.
Affordable projects here are cost-driven, so we offer primary-mill Fe500D where the consultant insists and approved secondary-mill bars where the spec allows.
Catholic families from the villages, industrial-estate workers and first-time buyers from Mira Road. That is who our inventory desk sells to when we take units here, which is why material-only barter in Vasai is typically 15–25% below the developer's rate rather than deeper.
Bundled with contracting in Vasai, the flats are taken at 35% below market and one work order covers structure and material.
| Grades | Fe500, Fe500D, Fe550D, Fe600 (IS 1786:2008) |
|---|---|
| Sizes | 8, 10, 12, 16, 20, 25, 32 mm; cut-and-bend and CNC pile-cage fabrication available |
| Brands | JSW Neosteel, Tata Tiscon, SAIL, Jindal Panther, Vizag, Kamdhenu, secondary mills on request |
| Lot size | 20 MT minimum per delivery; project supply 300 MT to 5,000 MT+ |
| Pricing basis | Daily Mumbai market rate + ex-yard freight, locked per delivery or per month as agreed |
| Documents | Mill test certificate, weighbridge slip, e-way bill, GST invoice on every truck |
Yes. We supply tmt bars to projects in Vasai and settle against flats, shops or units of the same project at an agreed barter rate, with GST invoices on every delivery and a registered agreement for the allotted units.
Yes. Any ratio works; many developers settle finishing-stage material in cash and structure-stage material in units.
Mill test certificate, weighbridge slip, e-way bill, GST invoice on every truck. Everything is mapped to the agreement ledger and reconciled monthly against the allotted value.
For material-only supply in Vasai the barter rate is usually 15–25% below the developer's current sales rate. When the material is bundled into a contracting work order, flats are valued at 35% below market.
Yes. Most developers bundle tmt bars with the structure work order so the whole package is settled in flats at 35% below market, with deliveries mapped to slab milestones.
We do. Once a unit is released to us against delivered value, selling it is our problem, not the developer's. The developer's sales pricing is not affected.
Flats allotted at 35% below the project's current market rate. Best when the developer wants zero cash outflow on structure.
Flats at 35% below market for the barter half; RA bills for the cash half. The most common structure for redevelopment schemes.
We also take pure cash contracts on competitive item rates when the developer prefers to keep inventory.
Architectural and structural sets, elevation, floor plates and the RERA number. Our estimators take off quantities and build an item-rate BOQ within three working days.
Per sq ft built-up or item-rate, shown for conventional RCC, Mivan or traditional as the structure allows, with barter, 50/50 and cash columns side by side.
Flats in the same project valued at 35% below today's rate. Work-order value divided by that rate gives the carpet area we receive; the unit schedule goes into the MOU.
Work order with milestone table, barter MOU, registered agreements for sale on the allotted flats, escrow or milestone release as the lender permits.
Mobilisation inside 15 days. Your PMC certifies milestones; flats release to us against certified value, RA bills cover any cash share.
Other services in Vasai:
Send the BOQ and the units you can allot. Proposal in 48 hours.