Supply of ready-mix concrete to Altamount Road projects, priced at daily Mumbai rates and settled in flats or units instead of cash.
Altamount Road and Carmichael Road form the most expensive kilometre in the country, where 1970s society buildings sit next to private residences and each redevelopment is a landmark in its own right.
Ultra-luxury redevelopment into 20 to 40-storey towers with full-floor 5 BHK apartments, private lobbies and multi-level basements.
Mixers stop at the road and a stationary pump pushes concrete up the slope; pour rates are lower, so we plan smaller pour zones and retarded mixes to avoid cold joints.
Luxury towers here specify M50 to M60 for cores and columns, self-compacting mixes for congested reinforcement, and pumped placement above 40 floors.
Industrialist families and top-tier professionals; each flat is negotiated individually and rarely advertised. That is who our inventory desk sells to when we take units here, which is why material-only barter in Altamount Road is typically 8–15% below the developer's rate rather than deeper.
Typical structure: concrete for the full RCC frame of a 20-storey tower is settled against 1 to 3 units, released against slab milestones. Combine it with barter contracting in Altamount Road for a single settlement at 35% below market.
| Grades | M20, M25, M30, M35, M40, M45, M50, M60; self-compacting and high-strength mixes |
|---|---|
| Plants | Partner plants across Mumbai, Navi Mumbai and Thane with 30–120 cu m/hr capacity |
| Pumping | Boom pumps (36–52 m), stationary pumps, night-pour slots for slab casts |
| Lot size | 6 cu m minimum; project supply 5,000 to 60,000 cu m |
| Pricing basis | Per cu m grade-wise, pumping and transit charges itemised |
| Quality | Cube test reports, slump at site, mix design approval from your PMC |
Yes. We supply ready-mix concrete to projects in Altamount Road and settle against flats, shops or units of the same project at an agreed barter rate, with GST invoices on every delivery and a registered agreement for the allotted units.
Material rates are either locked per delivery or reset monthly against a published index; the barter rate for units is locked for the supply period. Both mechanisms are written into the MOU.
Indicative proposal within 48 hours of receiving the BOQ, site meeting within the week, first delivery within 7 to 10 days of the signed MOU. 6 cu m minimum; project supply 5,000 to 60,000 cu m
Boom pumps (36–52 m), stationary pumps, night-pour slots for slab casts. The brand is fixed in the MOU; substitutions only with written approval from your PMC.
Cube test reports, slump at site, mix design approval from your PMC. Everything is mapped to the agreement ledger and reconciled monthly against the allotted value.
Mixers stop at the road and a stationary pump pushes concrete up the slope; pour rates are lower, so we plan smaller pour zones and retarded mixes to avoid cold joints.
Flats allotted at 35% below the project's current market rate. Best when the developer wants zero cash outflow on structure.
Flats at 35% below market for the barter half; RA bills for the cash half. The most common structure for redevelopment schemes.
We also take pure cash contracts on competitive item rates when the developer prefers to keep inventory.
Send architectural and structural drawings, elevation, floor plates and the RERA number. We take off quantities and build an item-rate BOQ.
Quote per sq ft built-up or item-rate, separately for conventional RCC, Mivan or traditional as the structure demands. Barter, 50/50 and cash options side by side.
Flats in the same project are valued at 35% below the current market rate. Work-order value ÷ barter rate = carpet area allotted to us.
Work order with milestone table, barter MOU and registered agreements for sale on the allotted flats. Escrow or milestone release as your lender permits.
Mobilise in 15 days. Milestones certified by your PMC; flats released to us against certified value, RA bills for any cash component.